Boost Reliability & Cut Grid Demand with BC Hydro’s ESI Program

Our team here at Commercial Lighting can assist you through the application process and discuss what solutions are best fit for your business and needs.

Boost Reliability & Cut Grid Demand with BC Hydro’s ESI Program

BC Hydro's Energy Storage Incentive (ESI) program offers businesses enhanced reliability and resilience while reducing strain on the power grid. By storing energy and using it strategically, businesses can lower peak demand charges, maintain operations during outages, and support sustainability by reducing reliance on diesel backup generators.

BC Hydro’s Incentive Offer

To support the adoption of ESS, BC Hydro provides valuable incentives for the purchase, installation, and operation of battery storage systems. Once installed, the system can automatically respond to grid conditions, discharging stored energy to power the facility while easing demand on the grid. The battery then recharges during off-peak hours, optimizing energy efficiency.

Our team here at Commercial Lighting can assist you through the application process and discuss what solutions are best fit for your business and needs.

How the Incentive Works

The incentive amount is based on the nominated battery capacity available for demand flexibility events and is calculated as the lesser of:

  • $10,000 per kW nominated.
  • $10,000 per kWh/4 nominated.
  • 80% of eligible project costs.

Businesses must meet the following criteria to qualify for BC Hydro’s energy storage incentive:

  • Be on a general service or irrigation rate under the Electric Tariff.
  • Install a new battery (previously purchased or installed systems are ineligible).
  • Have an operational smart meter.
  • Complete the required net metering or generator interconnection process.
  • Ensure the system is non-exporting to the grid.\
  • Install and energize an ESS that meets program requirements within 24 months of completing the interconnection study or application process.
  • Agree to a 10-year contract to provide demand flexibility services.
  • Provide reliable demand flexibility year-round with the following parameters:
    • Maximum event duration: 4 hours
    • Maximum daily frequency: 2 events
    • Minimum hours between events: 5 hours
  • Maintain at least 85% of nominated capacity for 85% of demand response events, assessed annually.
  • Connect to the BC Hydro software platform via IEEE 2030.5, SCADA, API, or an approved method for receiving event signals.

For more details, learn more about ESI & DERMS here or visit BC Hydro’s website here.

Why Consider Energy Storage?

By participating in BC Hydro’s program, businesses can:

  • Boost energy efficiency: Enhance resilience, reduce disruptions, and stabilize the grid while benefiting from financial incentives.
  • Cut costs: Lower electricity expenses by effectively managing peak demand charges.
  • Go green: Advance sustainability by minimizing reliance on diesel generators.
This is a powerful opportunity to future-proof your operations while cutting costs!
To learn more or begin the application process, connect with us today and we can help plan and answer any questions you may have.

Ready to start saving on energy consumption?

Reach out to our team to discuss your needs

Ready to get your EV Infrastructure up and running?

Recent posts

BC Hydro Offers Business Incentives for Energy Storage Systems (ESS)

Energy storage is a game-changer for efficiency. Understanding the technical aspects and incentive structure is crucial - and we can help.

Incentives for Multi-Unit Residential Buildings

BC Hydro has announced multiple incentives now available for multi-unit residential property.

Replacing Douglas Lighting Controls

With Douglas Lighting Controls technology being outdated, Commercial Lighting has the solution to help keep you up and running.